| : Reinforcing the power of the Bemposta II Dam |
| EDP - Gestão da Produção de Energia |
| Description: |
Design, supply and installation of electromechanical equipment and systems, of medium and low voltage, AC and DC auxiliaries for the power and security systems for the new hydroelectric power building. Includes generator, consisting of a Francis turbine and an alternator with a rated capacity of 191 MW / 212 MVA, hydromechanical equipment, equipment for lifting and moving people and loads, installation under tension of output transformer, group transformer with voltages of 417 KW/ 15 KW and power of 215 MVA and plants for emission of energy and interconnection at 400 kW. Implementation of the command and control system, facilities of general auxiliary services and facilities for safety of the Bemposta dam. |
| Local: |
Bemposta |
| Kick of: |
2008-04-24 |
| Conclusion: |
2011-12-31 |
| Market: |
ENERGY |
|
|
|
|
|
|
|